The Main parameter editing page allows you to set a variety of program-wide variables
including -
Date format: Change
the date display used in the Grids and throughout the program
Default cost
unit: Change the unit displayed for Currency items
Default duration
unit: Set the unit the program uses to indicate task duration assuming
that you type a number and don't enter the unit: h, d, w, or y (hour, day, week, year).
Default working
day: Set up to three different time ranges in your common working day.
Important: Remember
to use a 24-hour clock when entering this data.
Variable -
This allows you to set 4 different internal variables including -
- Hours in a day (defaults to 8)
- Hours in a week (defaults to 40)
- Hours in a month (defaults to 160)
- Hours in a year (defaults to 1920)
If your project
requires a longer or shorter day, week, month or year...select the appropriate
variable from the Variable combo box, then change the value in the Value editbox.
Click the Apply or OK button to save the changes.